Cambridge International A Level · Information Technology (9626)

Project management (A Level only): Practice Questions

5 multiple-choice questions marked as you go, and 5 written questions with worked solutions. All on Project management (A Level only).

10 questions26 marksFree, no account
Question 1
1 mark

In project management, what specific milestone or event does a deliverable represent?

Question 2
1 mark

A project manager is analyzing a project network using the Critical Path Method (CPM). An activity has an Earliest Start time of day \(8\), an Earliest Finish time of day \(14\), a Latest Start time of day \(11\), and a Latest Finish time of day \(17\). What is the total float for this activity?

Question 3
1 mark

A project manager needs to determine the critical path for a project with the following four sequential paths and durations from start to end:
- Path 1: Tasks A \(\rightarrow\) B \(\rightarrow\) E with a duration of \(18\) days
- Path 2: Tasks A \(\rightarrow\) C \(\rightarrow\) E with a duration of \(22\) days
- Path 3: Tasks A \(\rightarrow\) D \(\rightarrow\) F with a duration of \(15\) days
- Path 4: Tasks G \(\rightarrow\) H with a duration of \(20\) days
If the duration of Task C on Path 2 is reduced by \(3\) days, what is the new duration of the project's critical path?

Question 4
1 mark

In project management, which term is used to describe the period of time that a task can be delayed without affecting the project finish date or the start of a subsequent task?

Question 5
1 mark

When using the Critical Path Method (CPM) in project management, what is the primary characteristic of the tasks located on the critical path?

Question 6
3 marks

In Project management, a manager identifies the critical path for a new software development project. If a project consists of three sequential tasks on the critical path with durations of \(6\) days, \(10\) days, and \(5\) days, calculate the total project duration. State the specific effect on the final completion date if the first task in this sequence is delayed by \(3\) days.

Write your answer out first, then check it against the worked solution.

Question 7
5 marks

In project management and Critical Path Method (CPM) analysis, a non-critical activity has an earliest start time of day \(8\), a latest start time of day \(14\), and an estimated duration of \(5\) days. Calculate the total float of this activity and state the maximum number of days this activity can be delayed without delaying the overall project completion date.

Write your answer out first, then check it against the worked solution.

Question 8
3 marks

Explain how Project Management Software assists a project manager in allocation of resources when multiple tasks overlap in a schedule.

Write your answer out first, then check it against the worked solution.

Question 9
4 marks

A project manager is using a Gantt chart to coordinate tasks for a small software update. Refer to the diagram. Each unit on the horizontal axis represents one day.
(a) Calculate the total minimum number of days required to complete the project if Task B is dependent on Task A, but Task C can run independently.
(b) Describe one reason why a project manager would use a Gantt chart rather than a simple task list to monitor this project.

Write your answer out first, then check it against the worked solution.

Question 10
6 marks

A project manager is analyzing a software implementation project using Critical Path Method (CPM) and PERT analysis.

The project tasks, their durations, and immediate predecessor dependencies are given as follows:
• Task A: Requirements definition, duration = \(4\) weeks, no predecessor.
• Task B: Database design, duration = \(6\) weeks, depends on Task A.
• Task C: User interface prototype, duration = \(3\) weeks, depends on Task A.
• Task D: Core backend coding, duration = \(8\) weeks, depends on Task B.
• Task E: Frontend integration, duration = \(5\) weeks, depends on Task C.
• Task F: Final system deployment, duration = \(2\) weeks, depends on both Task D and Task E.

(a) Identify the two distinct paths connecting the start to the end of the project and calculate the duration of each path.
(b) Identify the critical path and state the minimum total project duration.
(c) Calculate the total float (slack time) for Task C.
(d) Explain the impact on the final project completion date if Task E is delayed by \(4\) weeks.

Write your answer out first, then check it against the worked solution.

* The content provided by thinka is generated by AI and may not always be accurate or up-to-date. Please use it as a supplementary resource and verify with official materials.

You've seen the model answer. Now get yours marked.

This page can show you how a good answer looks. It cannot tell you what your answer was missing. thinka marks your written work against the real mark scheme in about 15 seconds.

Want more questions like these? Get a fresh set on this topic, marked as you go.

Practise More