PMP Formulas Cheat Sheet: EVM Math, EAC Decision Tree & ECO Scenario Tactics

Cracking the Quantitative Shift in the Modern PMP Exam
For working professionals in Singapore preparing to sit the Project Management Professional (PMP) examination, quantitative questions often trigger unnecessary anxiety. A common misconception circulating in study groups across Raffles Place and Jurong is that you need to memorise dozens of convoluted formulas to survive the 180 questions. Under the current Project Management Institute (PMI) Examination Content Outline (ECO), rote mathematical drills have taken a backseat to situational interpretation. The exam rarely demands pure arithmetic gymnastics; instead, it tests whether you can diagnose project health and select corrective actions based on quantitative indicators.
This pmp formulas cheat sheet isolates the essential formulas that still matter under the current testing framework. Rather than forcing you to memorize endless static PMBOK equations, this guide equips you with the situational logic, decision rules, and mathematical anchors necessary to solve calculation and interpretation questions swiftly at test centres like Pearson VUE Tanjong Pagar. If you want to benchmark your test readiness, explore our professional exam preparation guides to see how modern predictive and agile frameworks intersect.
The Core Earned Value Management (EVM) Baseline
Earned Value Management measures project performance against scope, schedule, and cost baselines. Before running calculations, ground yourself in the three fundamental baseline metrics: Planned Value (egin{math}PVegin{math}), the budgeted value of work scheduled; Earned Value (egin{math}EVegin{math}), the budgeted value of work actually completed; and Actual Cost (egin{math}ACegin{math}), the realised cost incurred for work completed.
1. Variances (Difference Metrics)
Variances tell you the magnitude of deviation in currency units. A positive variance indicates favorable performance, whereas a negative variance signals trouble.
Cost Variance (CV):
egin{math}CV = EV - ACegin{math}
Interpretation: If egin{math}CV > 0egin{math}, you are under budget. If egin{math}CV < 0egin{math}, you are over budget.
Schedule Variance (SV):
egin{math}SV = EV - PVegin{math}
Interpretation: If egin{math}SV > 0egin{math}, you are ahead of schedule. If egin{math}SV < 0egin{math}, you are behind schedule.
2. Indices (Efficiency Ratios)
Indices reflect relative efficiency. A baseline score of egin{math}1.0egin{math} represents on-target performance. Anything below egin{math}1.0egin{math} indicates inefficiency.
Cost Performance Index (CPI):
egin{math}CPI = rac{EV}{AC}egin{math}
Interpretation: A egin{math}CPIegin{math} of egin{math}0.85egin{math} means the project is getting only egin{math}85egin{math} cents of value for every dollar spent.
Schedule Performance Index (SPI):
egin{math}SPI = rac{EV}{PV}egin{math}
Interpretation: An egin{math}SPIegin{math} of egin{math}1.15egin{math} indicates the project is progressing at egin{math}115egin{math}% of the planned rate.
The Estimate at Completion (EAC) Decision Tree
Forecasting formulas cause the most confusion on exam day because PMI tests four distinct permutations of Estimate at Completion (egin{math}EACegin{math}). The question prompt will rarely tell you which equation to use; instead, you must deduce the project context from situational clues.
Permutation 1: Current variances are atypical
Use this when an anomalous event (e.g., sudden equipment breakdown or vendor default) impacted past costs, but future work will proceed according to the original plan:
egin{math}EAC = AC + (BAC - EV)egin{math}
Permutation 2: Future work will maintain the current cost efficiency
Use this when historical cost performance is considered typical of future spending patterns:
egin{math}EAC = rac{BAC}{CPI}egin{math}
Permutation 3: Both cost and schedule performance impact remaining work
Use this when the project has strict milestone dates and poor cost efficiency must be balanced against schedule recovery:
egin{math}EAC = AC + rac{BAC - EV}{CPI imes SPI}egin{math}
Permutation 4: Initial estimates were fundamentally flawed
Use this when past assumptions are invalid and a complete bottom-up re-estimate of remaining work is required:
egin{math}EAC = AC + Bottom ext{-}up ext{ }ETCegin{math}
To-Complete Performance Index (TCPI)
The egin{math}TCPIegin{math} calculates the cost efficiency required on remaining work to achieve a specific management goal. It is the inverse of past efficiency: higher numbers indicate greater difficulty.
To achieve original Budget at Completion (egin{math}BACegin{math}):
egin{math}TCPI_{BAC} = rac{BAC - EV}{BAC - AC}egin{math}
To achieve revised Estimate at Completion (egin{math}EACegin{math}):
egin{math}TCPI_{EAC} = rac{BAC - EV}{EAC - AC}egin{math}
Diagnostic Rule: If egin{math}TCPI > 1.0egin{math}, remaining work must be completed significantly more efficiently than planned to stay within targets. If egin{math}TCPI > 1.2egin{math}, PMI situational logic often views this target as unrealistic without scope cuts or budget adjustments.
Schedule, Risk, and Communication Formulas
1. Critical Path and Float Calculations
Float (slack) dictates schedule flexibility. A critical path activity has zero total float.
Total Float (TF):
egin{math}TF = Late ext{ }Start (LS) - Early ext{ }Start (ES)egin{math}
or
egin{math}TF = Late ext{ }Finish (LF) - Early ext{ }Finish (EF)egin{math}
Free Float (FF): The amount of time an activity can be delayed without delaying the early start of any immediate successor:
egin{math}FF = Early ext{ }Start ext{ }(Successor) - Early ext{ }Finish ext{ }(Current) - 1egin{math} (or egin{math}0egin{math} depending on whether calendar day indexing starts at 0 or 1).
2. Three-Point Estimating (PERT Beta Distribution)
When tasks carry high uncertainty, the Program Evaluation and Review Technique (PERT) applies a weighted average favoring the most likely outcome (egin{math}Megin{math}) over optimistic (egin{math}Oegin{math}) and pessimistic (egin{math}Pegin{math}) durations:
egin{math}E = rac{O + 4M + P}{6}egin{math}
Standard Deviation (egin{math}
hoegin{math}):
egin{math}
ho = rac{P - O}{6}egin{math}
3. Communication Channels
This classic formula tests how team expansion drives communication complexity:
egin{math}Lines = rac{n(n - 1)}{2}egin{math}
where egin{math}negin{math} represents the number of stakeholders. Note: If a prompt says "four members are added to a team of six", egin{math}negin{math} changes from egin{math}6egin{math} to egin{math}10egin{math}.
Exam Room Tactics for Singapore Professionals
Singaporean candidates balancing tight work schedules often struggle with time management across the 230-minute test. To maximise your score efficiency on numerical questions:
1. Diagnose Before Computing: Read the last sentence of the prompt first. Often, the text gives you detailed numerical background only to ask: "Is the project currently over budget or ahead of schedule?" Look directly at egin{math}CPIegin{math} and egin{math}SPIegin{math}—if both exceed egin{math}1.0egin{math}, select the option describing good performance without opening the on-screen calculator.
2. Watch Out for Hybrid Contexts: Many modern PMP questions blend agile and predictive practices. If an agile release uses a burnup chart rather than traditional EVM, do not force an egin{math}EACegin{math} formula. Evaluate velocity and iteration burndown instead.
3. Leverage Automated Practice: Instead of re-reading PMBOK pages, train your diagnostic reflexes using adaptive simulators. By practising on an interactive PMP calculation platform, you can drill situational EAC selection under realistic exam timers.
Summary Cheat Sheet Table
Keep these fundamental relationships clear in your mind on exam day:
• egin{math}CV = EV - ACegin{math} (Positive is good)
• egin{math}SV = EV - PVegin{math} (Positive is good)
• egin{math}CPI = EV / ACegin{math} (egin{math}> 1.0egin{math} is good)
• egin{math}SPI = EV / PVegin{math} (egin{math}> 1.0egin{math} is good)
• egin{math}EAC = BAC / CPIegin{math} (Typical future spending)
• egin{math}EAC = AC + (BAC - EV)egin{math} (Atypical past deviations)
• egin{math}PERT = (O + 4M + P) / 6egin{math}
• egin{math}Channels = n(n - 1) / 2egin{math}
To build confidence and master situational decision-making across all ECO domains, discover how Thinka uses AI-driven practice to personalise your revision path and help you clear your PMP on the first try.
Related posts
- Oct 23, 2026
CFA Level 3 Pathways: Portfolio Management, Private Wealth or Private Markets for Singapore Finance?
Compare CFA Level 3 pathways: Portfolio Management, Private Wealth, and Private Markets. Discover syllabus weights, exam mechanics, and Singapore career ROI.
- Oct 17, 2026
Best State for International Students to Take CPA: Eligibility, SSN Waivers & Evaluation Matrix
Select the best US CPA state board for international candidates. Compare SSN waivers, 120 vs 150 credit rules, NIES vs FACS, and 3-year degree bridging.
- Oct 14, 2026
CFA Level 1 vs Level 2: The Vignette Shift, Weighting Jumps & Singapore 350-Hour Plan
Compare CFA Level 1 vs Level 2: decode the 88-question vignette case study format, FSA and Equity weight jumps, and build a 350-hour Singapore study roadmap.
- Oct 11, 2026
CPA Exam Blackout 2027: Prometric UI Shift, Seat Crunches & Singapore Sitting Tactics
Navigate the 11-day July 2027 CPA exam blackout. Discover Prometric UI overhaul details, Q3 score lag impacts, and credit retention plans for Singapore professionals.