An Operations strategy that prioritises flexibility is most likely focused on which objective?

ข้อ 2
1 คะแนน

Which of the following describes a significant potential limitation for a business that relies heavily on Just-in-Time (JIT) inventory management as its main operations strategy?

ข้อ 3
1 คะแนน

A construction firm is using Critical Path Analysis (CPA) to manage a new building project. Activity X has a duration of 6 days. The Earliest Start Time (EST) for Activity X is Day 10, and the Earliest Start Time (EST) for the following activity is Day 18. What is the free float for Activity X?

ข้อ 4
1 คะแนน

A manufacturing business is considering a process innovation by introducing Artificial Intelligence (AI) into its quality management operations. What is the most likely primary objective of this operational strategy?

ข้อ 5
1 คะแนน

In a highly competitive market, how does the implementation of an Enterprise Resource Planning (ERP) system specifically support a business's operations strategy for flexibility?

ข้อ 6
4 คะแนน

Explain how the implementation of an Enterprise Resource Planning (ERP) system can improve the operational efficiency of a manufacturing business.

ลองเขียนคำตอบด้วยตัวเองก่อน แล้วค่อยเทียบกับวิธีทำ

ข้อ 7
5 คะแนน

In a Critical Path Analysis (CPA), an activity has an Earliest Start Time (EST) of 10 days, a duration of 6 days, and the EST of the following activity is 20 days. Calculate the free float for this activity and explain its significance for project scheduling.

ลองเขียนคำตอบด้วยตัวเองก่อน แล้วค่อยเทียบกับวิธีทำ

ข้อ 8
4 คะแนน

A manufacturing firm is planning its operations strategy and needs to determine the critical path for a project. If activity C has an earliest start time (EST) of 12 days, a duration of 5 days, and its latest finish time (LFT) is 20 days, calculate the total float for this activity.

ลองเขียนคำตอบด้วยตัวเองก่อน แล้วค่อยเทียบกับวิธีทำ

ข้อ 9
5 คะแนน

A manufacturing company is considering the adoption of lean production to reduce waste and improve its competitive position.
a) Explain the concept of Kaizen as an operational strategy.
b) Analyse two ways in which Enterprise Resource Planning (ERP) could help the company improve its inventory control and capacity utilisation.

ลองเขียนคำตอบด้วยตัวเองก่อน แล้วค่อยเทียบกับวิธีทำ

* เนื้อหาของ thinka สร้างโดย AI อาจไม่ถูกต้องสมบูรณ์ในทุกกรณี กรุณาใช้เป็นสื่อเสริมและตรวจสอบกับเอกสารอ้างอิงอย่างเป็นทางการ

คุณเห็นเฉลยแล้ว ทีนี้มาตรวจคำตอบของคุณบ้าง

หน้านี้บอกได้ว่าคำตอบที่ดีเป็นอย่างไร แต่บอกไม่ได้ว่าคำตอบของคุณขาดอะไร thinka ตรวจข้อเขียนของคุณตามเกณฑ์ให้คะแนนจริงในราว 15 วินาที

อยากฝึกโจทย์แบบนี้เพิ่มไหม เริ่มฝึกหัวข้อนี้ได้เลย ตรวจให้ทันทีทุกข้อ

เริ่มฝึกเลย