What is the primary purpose of a business using Critical Path Analysis (CPA) during the planning phase of a large-scale construction project?
Pearson Edexcel A Level · Business (9BS0)
Critical Path Analysis:練習問題
その場で採点される選択問題 5 問と、解説つきの記述問題 3 問。すべて「Critical Path Analysis」からの出題です。
In a Critical Path Analysis network, if Activity C has an Earliest Start Time (EST) of 12 days and a duration of 5 days, and the succeeding Activity D has an EST of 20 days, what is the total float for Activity C?
Which of the following is a significant limitation of using Critical Path Analysis for a business entering a highly uncertain and dynamic global market?
Which of the following best describes an activity that lies on the critical path of a project network?
A project involves four sequential activities: A, B, C, and D.
- Activity A: duration 4 days, no predecessors.
- Activity B: duration 6 days, follows A.
- Activity C: duration 5 days, follows A.
- Activity D: duration 3 days, follows both B and C.
What is the Earliest Start Time (EST) for Activity D?
In a project network diagram, what is the meaning of the Earliest Start Time (EST) for a specific activity?
まず自分で答えを書いてから、解説と照らし合わせましょう。
A project includes Activity C, which has a duration of 5 days. The Earliest Start Time (EST) for Activity C is day 8, and its Latest Finish Time (LFT) is day 15. Calculate the total float for Activity C.
まず自分で答えを書いてから、解説と照らし合わせましょう。
In a complex network diagram, an activity has an EST of day 10 and an EFT (Earliest Finish Time) of day 14. Its LFT is day 18. Determine the duration of the activity and its Latest Start Time (LST), showing your working.
まず自分で答えを書いてから、解説と照らし合わせましょう。
※ thinkaのコンテンツはAIにより生成されているため、内容が正確でない場合があります。補助教材としてご使用いただき、公式の教材と合わせてご確認ください。
模範解答は見ました。次はあなたの答案を採点します。
このページは良い答案の形を示せますが、あなたの答案に何が足りないかは教えられません。thinka は実際の採点基準に沿って記述答案を約 15 秒で採点します。
同じような問題をもっと解きたい?このトピックの新しい問題を、解きながら採点。
練習を始める