题目 1 · Short Answer & Recall (RIBA Plan of Work, Roles, Definitions)
15 分(a) State the name and year of the plan that sets out the eight main stages of the construction cycle used in the UK construction industry. [2]
(b) List the eight stages of this plan, in the correct order. [8]
(c) Describe what occurs during the 'Handover and Close Out' stage. [3]
(d) Identify ONE type of low-rise building that would typically be classified as 'community' use, giving an example. [2]
(b) List the eight stages of this plan, in the correct order. [8]
(c) Describe what occurs during the 'Handover and Close Out' stage. [3]
(d) Identify ONE type of low-rise building that would typically be classified as 'community' use, giving an example. [2]
查看答案详解收起答案详解
解题
(a) The plan is the RIBA (Royal Institute of British Architects) Plan of Work, published in 2013. (b) The eight stages, in order, are: Strategic Definition; Preparation and Brief; Concept Design; Developed Design; Technical Design; Construction; Handover and Close Out; and In Use. (c) The Handover and Close Out stage occurs after the physical construction work is complete; the finished building is formally handed over to the client, building services (such as heating and electrical systems) are tested and commissioned to confirm they work correctly, any outstanding minor defects ('snagging') identified during a final inspection are rectified, and the client receives relevant documentation (such as operating manuals and warranties) before the project formally closes. (d) A community building is a low-rise building used by the public for shared civic, educational or health-related purposes; examples include a school, a hospital, a library or a health centre. Final answer: (a) RIBA Plan of Work, 2013; (b) the eight stages listed in order above; (c) handover, testing/commissioning and snagging as described; (d) a community building, e.g. a school.
评分标准
(a) [1] correct name (RIBA Plan of Work); [1] correct year (2013). (2 marks) (b) [1] per correctly named and correctly ordered stage, up to a maximum of [8]; deduct no marks for minor wording variation provided the meaning is clear and the order is correct. (8 marks) (c) [1] basic description; [2] adequate description covering handover and/or testing; [3] competent description covering handover, testing/commissioning AND snagging/defect resolution. (3 marks) (d) [1] correctly identifies 'community' as the building type; [1] gives a valid example (e.g. school, hospital, library, health centre). (2 marks) All other valid responses will be given credit. Total 15 marks.